We were unfairly blamed for station opening delay, says NR

RAIL

Andrew Forster
01 February 2019
 

An inquiry into why a new railway station in Warwickshire opened more than a year late has raised questions about how local authority-promoted rail projects are best delivered. 

Network Rail says it was unfairly blamed for the delay to opening the £13.2m station at Kenilworth. It says the “vast majority” of the delay was caused by “poor control and management of the contractor” by a third party.

The station, on the single track Leamington Spa-Coventry line,...

+89% more

 

Senior Programme Development Officer
East Midlands Combined County Authority
Chesterfield / Hybrid
£36,648 - £41,418
Senior Programme Development Officer
East Midlands Combined County Authority
Chesterfield / Hybrid
£36,648 - £41,418
Senior Transport Planner
London Borough of Camden
5 Pancras Square, London, N1C 4AG
£44,579
View all Vacancies
 
Search
 
 
 

TransportXtra is part of Landor LINKS

© 2024 TransportXtra | Landor LINKS Ltd | All Rights Reserved

Subscriptions, Magazines & Online Access Enquires
[Frequently Asked Questions]
Email: subs.ltt@landor.co.uk | Tel: +44 (0) 20 7091 7959

Shop & Accounts Enquires
Email: accounts@landor.co.uk | Tel: +44 (0) 20 7091 7855

Advertising Sales & Recruitment Enquires
Email: daniel@landor.co.uk | Tel: +44 (0) 20 7091 7861

Events & Conference Enquires
Email: conferences@landor.co.uk | Tel: +44 (0) 20 7091 7865

Press Releases & Editorial Enquires
Email: info@transportxtra.com | Tel: +44 (0) 20 7091 7875

Privacy Policy | Terms and Conditions | Advertise

Web design london by Brainiac Media 2020