HS2 chief sticks by £65bn total for delivering London-Birmingham line

Rhodri Clark
25 January 2024
Sir Jonathan Thompson: It is the Government’s long-standing policy that infrastructure estimates are updated only at spending review points
Sir Jonathan Thompson: It is the Government’s long-standing policy that infrastructure estimates are updated only at spending review points

 

Sir Jonathan Thompson, executive chair of HS2 Ltd, has told MPs that the current cost of phase 1 of the high speed line between London and Birmingham, could now reach £65bn. He told the Transport Select Committee that the project is currently estimated to cost between £49bn and £56.5bn at 2019 prices, but that updating costs to current prices would add another £8bn-£10bn.

“So we are looking in the region of £60 billion to £65 billion for phase 1,...

+86% more

 

Healthy Streets Traffic Engineer Technical Lead x2
Bristol City Council
100 Temple Street Redcliffe Bristol BS1 6AN
BG13 £45,718 - £48,710
Healthy Streets Principal Traffic Engineer
Bristol City Council
100 Temple Street Redcliffe Bristol BS1 6AN
£38,296 to £ £43,421 (Career Grade BG12)
Senior Transport Planner
London Borough of Camden
5 Pancras Square, London, N1C 4AG
£44,579
View all Vacancies
 
Search
 
 
 

TransportXtra is part of Landor LINKS

© 2024 TransportXtra | Landor LINKS Ltd | All Rights Reserved

Subscriptions, Magazines & Online Access Enquires
[Frequently Asked Questions]
Email: subs.ltt@landor.co.uk | Tel: +44 (0) 20 7091 7959

Shop & Accounts Enquires
Email: accounts@landor.co.uk | Tel: +44 (0) 20 7091 7855

Advertising Sales & Recruitment Enquires
Email: daniel@landor.co.uk | Tel: +44 (0) 20 7091 7861

Events & Conference Enquires
Email: conferences@landor.co.uk | Tel: +44 (0) 20 7091 7865

Press Releases & Editorial Enquires
Email: info@transportxtra.com | Tel: +44 (0) 20 7091 7875

Privacy Policy | Terms and Conditions | Advertise

Web design london by Brainiac Media 2020